Real-time production control for large-scale earthworks operations

Case snapshot
Project
Fargo-Moorhead Diversion Channel
Budget
USD 1.2 billion
Year
May 2021 – Ongoing
Customer
ACCIONA, S&B GROUP, & NORTH AMERICAN CG
Location
Fargo, North Dakota, USA
Project type
Dams and earthworks
Scope
Real-time production monitoring and operational control across 24/7 earthmoving operations
Solution
Digital production control platform for earthworks execution management
The challenge: Earthworks at unprecented scale
The Red River Flood Diversion project presented a uniquely complex operational challenge: coordinating and controlling earthworks production across an immense construction footprint, with continuous activity running 24/7.
The project involved moving 48 million cubic yards of material, requiring precise coordination of equipment, operators, haul distances, and production targets across multiple simultaneous work fronts.
Previous attempts to solve similar challenges using proximity-based tracking systems had proven too rigid for the dynamic realities of earthmoving operations.
Traditional alternatives could track time and volumes, but lacked the operational detail required to understand how production was being achieved.
We needed much more than production totals. We needed detailed operational intelligence to understand exactly how work was being performed.
Alejandro Fernández García
48M yd³
MATERIAL MANAGED THROUGH DIGITAL PRODUCTION CONTROL
200 Reports/Day
AUTOMATED WITH REAL-TIME PROCESSING
6 FTE Saved
ADMINISTRATIVE WORKLOAD ELIMINATED
24/7 Visibility
CONTINUOUS OPERATIONAL OVERSIGHT
The solution: Built for operational adaptability
Drawing on earlier experience in New Zealand, Acciona chose to continue developing its own platform rather than adopt off-the-shelf alternatives.
“External tools could track volumes, but they couldn’t provide the operational detail we needed.”
The result was a specialized earthworks control system designed around field realities.
CORE CAPABILITIES
Production Reporting
Digital capture of field production data
Operational Alerts
Immediate visibility into deviations
Data Integration
Unified operational data flows
Shift Line-Up
Real-time workforce coordination
Equipment Monitoring
Continuous activity tracking
Historical Analytics
Historical Analytics Long-term production intelligence
Implementation: 18 months to full deployment
The platform required 18 months of refinement, with Fargo’s extreme environmental conditions adding significant hardware challenges.
Close collaboration between project teams and local engineering support transformed the system into a reliable field-ready solution.
“It was a difficult road, but once everything came together, the results were clear.”
The transformation: from reporting to real time control
The project generated approximately 200 production reports per day across continuous operations.
Without automation, processing this volume would have required significant administrative effort and delayed operational response. Instead, the platform delivered instant visibility and enabled immediate intervention when needed.
“Real-time visibility allows operational intervention as things happen—not days later.”
Looking ahead: scaling earthworks intelligence
Following its success in Fargo, the solution is being considered for future large-scale earthworks projects, including upcoming developments in New Zealand.
Its long-term value lies in building a production intelligence database capable of improving future planning, productivity, and cost optimization.
I’m proud to have contributed to such a complete earthworks solution.
Alejandro Fernández García
Impact at a glance
Real-time visibility across continuous earthworks operations
Automated processing of ~200 daily production reports
Elimination of manual reporting delays
Avoided need for 5–6 additional administrative staff
Faster operational response to field deviations
Improved production accuracy and reliability
Valuable historical database for future optimization
Scalable model for future earthworks projects